Sunday, October 1, 2023
Uncategorised

Product development procedure of Honda car component

Product development procedure of Honda

Front end Loading

Before starting, you should have knowledge about process /product and detailed knowledge of Drawing.

So supplier has to do front end loading, product feasibility along with CFT. So entire product value can be understands and an approach could be build to start development of component.

Development of each component is done as per APQP. So we have knowledge about APQP-as we know 5 phase. It could be tough for those have not worked in industries for Honda (Specially), because some event terminology and requirement could confuse fresher.

  1. Planning phase 
  2. Product Design
  3. Process Design  
  4. Product/process Validation
  5. Feedback , Assessment  & Corrective action

Obviously development will be done as per APQP, but customer events & requirement could be specific. So we have to know those specific requirements as well as we have to know how to work as per those events.

Generally business is awarded on the basis of supplier selection after tech review meeting with customer. Sometime suppliers are selected after lot of review meetings.

OK let’s say- Your Company is identified as possible source of supplier for an OEM (HONDA).

OEM will release RFQ and will request quotation.

Supplier checks feasibility and confirm with quotation. If customer find that deal OK as per comparison with other supplier.

OEM issue LOI and request for Proto based parts. And if trial OK, preparation will be done for mass production. After all successful trials in development phase –Mass production is started. Supply is continuing at OEM on regular basis.

This was short description “How parts are development” but this is not simple as it seems, lot of work is done to bring any component in mass production successfully.

So here we will understand that process in details:-

Here I will take HONDA as OEM (The customer). Well we know what Honda do- Makes cars, many automotive works.

Vehicle Body parts:- see below picture 

A car has lot of component, we basically divide component is three categories:-
  1. Mision parts
  2. Engine parts
  3. Frame parts

Above three categories of parts are further classified in A, B, C & S ranks.

A – Critical to Quality, S – Safety part.

There are many categories, apart from these other categories are:- Electrical parts, chassis parts, Equipment, standard and semi standard parts, Body parts.

Now before going to direct development, we have to understand customer drawing. Basically drawing vary customer to customer, in Honda case they provide special symbols and abbreviation.

Understanding Honda product drawing


Double crossed line, show that symbol is not applicable for this part.

First 2 symbols from left side are -GRADE-1 & 2 To Judge General Tolerance on Dimensions.
Rest 3 Symbols are for TOLERANCE CLASS INDICATION (HIGH, MEDIUM, and LOW ACCURACY) AS PER HES A2135-99.

Title Blocks of HONDA product Drawing

What are Honda Part category?

  1. HS:- Safety part [PARTS WHICH LOSE IMPORTANT FUNCTIONS & MAY CAUSE SERIOUS ACCIDENTS WHEN FUNCTION FAILURE OCCURS ]
  2. HA:- PARTS WHICH LOSE IMPORTANT FUNCTIONS & MAY RESULT IN SERIOUS ACCIDENTS WHEN FUNCTIONAL FAILURE OCCURS, BUT WHICH SHOW SOME SIGN SO THAT SAFETY PRECAUTIONS CAN BE TAKEN.
  3. HB: – PARTS WHICH LOSE IMPORTANT FUNCTIONS WHEN FUNCTIONAL FAILURE OCCURS DO NOT RESULT IN SERIOUS ACCIDENTS.
  4. H:– Other than above
Most common terminology used for events of product development is as followed:-
  1. PP –Proto part
  2. MPP- Mass production part
  3. PILOT-Verification of mass production condition
  4. SOP-Start of Production
As I have told, customer wise events name changed. Honda use even name as below:-
  1. E-Dan & M-Dan
  2. Dan Event
  3. Dankaku Event
  4. Hinkaku Event
  5. Ryokaku Event

E-Dan even for Engine part only.  M-Dan is for mission part only. Dan, Dankaku, Hinkaku and Ryokaku events are for CBU.

Ryoshi:- Pre mass production trial. Honda check part fitment in CBU.
Suppliers Activities are align with Honda company activities.
 
From the above picture we see Honda events name along with Honda QAD activity throughout product development. Meaning of these codes is explained below.
 
P0:-Stand for only Planning [PLANNING PROPOSAL BY CST TEAM +PLANNING INTIATION AND MODEL FIX- DRAFT PLANNING] (P0=A000+A001+P1)
 
P2:- Stand for PLANNING FIX AND PROCEED FOR PROTO- COST/INVESTMENT ALL FIX
QDG1:- FEW PART DIE GO AHEAD
QDG1:- ALL PARTS DIE GO AHEAD
D1:- DESIGN FIX
E2:ACHIEVEMENT APPROVAL, M/P GO
E3:- REPORT AFTER 3 MONTHS OF M/P
Note: – CST is approval authorities for Design direction.
 
 

A000=PLANNING PROPOSAL BY CST TEAM

A001=DEVELOPMENT INSTRUCTION, CONCEPT/BASIC DESIGN APPROVAL

P1=PLANNING INTIATION AND MODEL FIX- DRAFT PLANNING

Up to A001-We do feasibility Check:- Honda will check whether there will be requirement of new supplier/Critical supplier (If new supplier- Honda will do system Audit-QAV2-1).

A000; A001; P0, P1 these activities are done at Honda Company. Up to P2 Honda finished planning, now moving to Proto part making. So accordingly they will make development plan and will share RFQ to supplier.

So Kickoff has been planned after P2, now working will be start at supplier end. Honda QAD will request following documents after kickoff from supplier.
MCP; TSS Req (Tool Summary Sheet); LCS REQ (Localization Check sheet-Supplier Details); Part MCP (Manufacturing Control Plan); Kakotora; Spec Test Plan
 
After Kickoff planning to be done at supplier as well as Honda, in which Part study check sheet is made at Honda as well as supplier(change point with existing part/process), QAV point verification (Jointly), MQS and QA Matrix (Supplier End); QD Matrix(Honda-Part Rank); Initial PQCT (Control Plan).
 
QAV2-2 will be planned before tools go ahead (QDG2). In QAV2-2 Honda verify Supplier Planning (Preparedness).
 
Following points to be verify by Honda QAD:-
  1. MCP CHECK (Shoken: T1)
  2. TOOLING PLAN
  3. INSP FIXTURE CONCEPT
  4. SPEC TEST PLAN
  5. KAKOTORA & MQS
  6. HOMOLOGATION PLAN
  7. OEE PLAN CHECK
  8. CONCERN (If Any 
After successfully verification Honda issues Tool Go ahead to supplier. Go ahead is done in two stage, First go ahead for some tools and second Go ahead for all tooling.
After first Go ahead- Supplier starts tooling design, arrange tooling material, drawing the tool, overall schedule & FIG. 
Second Go head is given after verification of MCP, QA Matrix & PAC-V simulation (Cp/Cpk conformation of 100% tolerance dimensions).
After second Go ahead part development is start on the basis of fixed drawing.
E1= QDG2+D1 (All die fixed + Issue Final drawing)
 
Tool trial is done to mature the level. Parts made on trials are sent to lab for spec testing. Target for tool level is different event and categories wise. 

Part Categories/Event
Dan
Dankaku
Hinkaku
Ryokaku
Engine Part
T3
LT1
R1
R1
Mission part
T3/LT1
LT1
R1
R1
Frame Part
T1
T3
T4/LT1
R1
All tooling trial done before making proto part for Honda. (Dan event Part)

QAV2-3 is planned by Honda. QAV2-3 is planned before Dankaku event, Purpose of audit is progress check.
Following points are verified in QAV-2 step 3 audit:-
  1. MCP REVIEW
  2. TOOLING COMPLETE
  3. INSP FIXTURE APPROVAL
  4. R/ MATERIAL APPROVAL
  5. EQUIP. PROGRESS CHECK
  6. PACKAGING SAMPLE SUBMIT
  7. HOMOLOGATION CERTIFICATE
Parts are made for Dankaku event and delivered to Honda Company.
 
QAV2-4 is planned by Honda, purpose is to Quality Verification. (Major Audit) 
Following points are verified in QAV 2 Step-4 Audit:
  1. PART CHK AS PER EVENT TGT
  2. FITMENT CONFIRMATION
  3. QA M/C VALIDATION AS PER CHK-SHEET (L/TEST & WELDING)
  4. MIN-MAX STUDY OF PROCESS PARAMETERS (FOR SPECIAL PROCESS)
  5. CONF. OF PAC-V, KAKOTORA, ETC
  6. PQCT APPROVAL
  7. LIMIT SAMPLE FREEZE
  8. SPEC TEST REPORT CONF
  9. M/P READINESS CHK
After that QAV2-5 audit is planned, Planning is done before Ryokaku. Purpose is verification of mass production readiness. For this trial we do 2H and 200 parts manufacturing whichever is later.
Following points are verified in QAV2 Step 5:
  1. MCP REVIEW
  2. R1 TRIAL EVALUATION
  3. Cp / Cpk VERIFICATION (100% PAC-V A RANK)
  4. M/P READINESS EVAL.
  5. PACKING/IDEN. CONFIRM
  6. PROCESS TACT VERIFY
  7. MANPOWER TRG.COMPLETE
  8. Safety Declaration (ANGEN SANGEN)
Note: – Separate audit is planned for Anzen Sangen) by Honda Company. Separate article is written for angen sangen audit.

Honda QAD handover these documents to Mass Production team, [(PQCT, INSPECTION  STANDARDS, LIMIT SAMPLES, TEST RESULTS, CAPACITY SHEETS, LOT CONTROL SHEETS, PACKAGING STANDARDS].

Before tools GO ahead Honda checks manufacturing confirmation in term of Drawing dimensions, spec, tool design.
 
MCP is verified in each QAV audit. MCP stand for manufacturing control plan ,purpose of MCP is to plan supplier activity in line with Honda Event, so that required level of part can be achieved at each event.
In MCP supplier plan should be in advance to Honda Event, micro plan to tool manufacturing, Spec test plan should be advance to Honda events and Part/process plan should be clearly visible. 
QAV audits check common verification items, these items come under following section/area:
  1. Production Preparation
  2. Finishing Quality of product
  3. Standards
  4. Education and training
  5. Quality Strategy
  6. In process Quality Control
  7. Control at suppliers (Tier-2, 3)
Basically all above mention activity study is applicable for product development of Engine related components. Since Engine/Mission/Frame related component are could be belong to entire engine system.
 
But process which i have mention in this blog is same for almost every component of Honda Vehicle. May be change depend case to case study. If you have any concern or suggestion contact me on mail I.D- jewsfamily01@gmail.com
 
Based upon functioning engine are divided into 5 circuit.
  • Air Circuit Diagram for AIR FLOW IN DIESEL ENGINE:-
  • DIAGRAM FOR COOLANT FLOW IN DIESEL ENGINE:
  • DIAGRAM FOR FUEL FLOW IN DIESEL ENGINE:-

Learnmytool

Hi.. welcome to learnmytool.com blog. Professional Engineer, blogger and tech educator. This blog is being managed since 2020. Purpose of this blog website is to get connected with those people who are interested in learning technical skills and are doing work in industries. Also we create content to help people in need. I am reachable, click on contact page for any support. Thank You

2 thoughts on “Product development procedure of Honda car component

  • Product samples may already be available at this stage, and with volume manufacturing imminent, sales are on the horizon. A sales organization is now needed. Depending on the end use market, sales people with direct experience and human networks in the end use applications, and a specific set of language skills, may be required. strategic thought leadership

  • All MEMS devices have sensitivity to temperature due to material coefficient of thermal expansion (CTE) as well as mismatches in CTE to attached materials. For example, in most systems, the MEMS is mounted in a package that is mounted to a printed circuit board (PCB), which can have a CTE that is 6 times greater or more than a silicon-based MEMS [4]. As the PCB undergoes heating and cooling, the PCB exerts mechanical forces on the package , and in turn, the MEMS die. These forces can cause distortions in the MEMS output signal. The package , if designed appropriately, could serve as a mechanical buffer between the MEMS die and the PCB. In this manner, the role of mechanically isolating the MEMS from the PCB could be partitioned to the package, instead of the MEMS die, to enable simplification of the MEMS design and fabrication. thought leadership content

Comments are closed.